In short
- A factory audit checklist tests three things: which legal entity makes the goods, what the bottleneck line can produce per week, and which operations leave the building.
- Floor area is not capacity. Capacity is the hours the bottleneck station actually runs, divided by the cycle time for your operation, multiplied by the yield you see.
- Write the seller's legal name and USCC, the AQL and inspection level, the subcontracted operations and the Incoterm with its named place into the RFQ.
A factory audit is a structured site visit that verifies who legally makes a product, how much that site can produce, and whether the equipment, records and quality system support the specification you are buying. It ends in findings, not a certificate.
A supplier visit and a factory audit look identical and answer different questions. A visit confirms that a showroom, a sample room and someone who answers emails exist. An audit establishes which entity controls the line, and whether that line has hours free in the week your order is promised.
01The licence names a company, not a factory
Every company trading or manufacturing in China holds a business licence showing an 18-character unified social credit code (USCC), registered capital, business scope and a registered address. Those fields fix an identity, not ownership of the building where your order is made.
Check the licence first because that identity must appear everywhere else. Search the USCC at gsxt.gov.cn, then compare the registered address with the production address in front of you. An office registration and a works 40 km away is common, and not automatically a problem. It is a question.
| Document | Establishes | Does not establish | Line to add |
|---|---|---|---|
| Business licence | Legal name, USCC, scope, address | Ownership of the site | Seller, USCC and bank account must match |
| Proforma invoice | Who sells and on what terms | Who makes the goods | Production address on the invoice |
| ISO 9001 certificate | A system audited within a scope | Product conformity or spare hours | Certificate number, scope and expiry |
| Test report | One sample, one method, one date | That your batch will match | Product, thickness and method named |
| Packing list | Cartons, quantities, marks | What is inside the cartons | Every carton mapped to supplier and item |
An unverified document is a question, not a finding.
A trading company and a factory can publish the same list, quote from the same photograph and hand over the same sample. The audit follows one order through the works: cutting list, machine, operator record, carton label.
Decision rule: licence, invoice and bank account must name the same legal entity. Where they differ, get the relationship in writing.
02Capacity is a schedule at the bottleneck
Capacity is not floor area, headcount or the number of machines in a row. It is the output of the slowest station your product passes through, over the hours that station runs.
Take a nesting CNC that cuts one 2,440 × 1,220 mm board in about 6 minutes: on an 8-hour shift at 80% utilisation it finishes 64 boards a shift, and two shifts over five days without a breakdown is 640 boards a week. That figure, not a website claim, is what your date rests on.
Utilisation is the number quotes leave out. Ask how many shifts ran this week, which station was the constraint, and what is booked on that station for the next four weeks. Equipment sized for three shifts and running one has spare hours in theory, not people.
Decision rule: ask for capacity in the unit your order is made in, whether boards, frames, doors or linear metres of edge banding, and ask which station limits it.
Catalogue reference: how sourcing, inspection and consolidation are coordinated — models, dimensions and finishes for the directions discussed above.
03Read the equipment against your drawing
An equipment list is a claim about capability. A machine set up for another product is not capability for yours, and a machine that cannot hold your tolerance produces a reject you pay for twice.
| Operation | Equipment | Verify on site | Clause for the RFQ |
|---|---|---|---|
| Panel cutting | Beam saw or nesting CNC | Sheet 2,440 × 1,220 mm; blade; squareness | Square within 0.5 mm per metre |
| Edge banding | Automatic edge bander | Tape 0.4–2 mm; glue; end trim | 1 mm ABS, PUR glue, radiused |
| Drilling | Multi-spindle borer | 32 mm pitch; pattern | System 32 to match the drawing |
| Veneering | Hot press | Platen against the largest part | Press record per batch |
| Finishing | Spray booth | Booth type; drying room; film gauge | Finish, gloss and film thickness |
| Packing | Carton line | Board grade; corners; drop test | Carton specification and drop test |
Tolerances are RFQ requirements, not values to assume.
The check is small: hand the operator one part from your drawing, watch it being cut, then measure it. A factory that makes your product will not hesitate. One that assembles bought-in parts explains why that is difficult.
Decision rule: every dimension that matters must map to a machine that can hold it and an instrument in calibration.
04The line that is not running is the finding
A stopped line means one of three things: no orders for that product, the product is made elsewhere, or the line is waiting on material. Each has a different consequence for your order.
Idle capacity is not automatically good news. An empty bench can mean a factory is available and keen, or short of work for a reason that will reach your order too. An idle line beside a busy one often means you run between larger jobs.
- Ask which station is the constraint this week, then stand there for 30 minutes.
- Count work in progress at each station against the daily output claimed.
- List the operations that leave the building, such as glass, stone tops or upholstery, and name who does each.
- Follow one carton label back to the order, drawing revision and packing date.
- Ask what the factory made last week for a customer buying your product type.
Decision rule: if the operation that decides your quality is subcontracted, the audit includes the subcontractor, or the finding is incomplete.
05Records, calibration and the sampling plan
An ISO 9001 certificate is a management-system certificate: a system was audited within a stated scope on a stated date. It does not say your cabinet will be square. Check that the scope names your product, that the body is accredited and that the certificate is live on the register. Certificates run three-year cycles with annual surveillance.
Calibration is the quieter test. A calliper with no calibration sticker is an opinion. Ask for the register, pick three instruments at random and match the sticker date to the entry.
Acceptance sampling under ISO 2859-1 sets the sample size from the lot size and inspection level, then the acceptance number from the AQL. General level II with AQL 2.5 for major defects and 4.0 for minor is a common starting point; state it rather than inherit it.
| Lot size | Code | Sample | Accept | Reject |
|---|---|---|---|---|
| 501–1,200 | J | 80 | 5 | 6 |
| 1,201–3,200 | K | 125 | 7 | 8 |
| 3,201–10,000 | L | 200 | 10 | 11 |
From ISO 2859-1 Tables 1 and 2-A. Define defect classes in the purchase order.
A visual inspection cannot confirm composition or hidden performance. Formaldehyde class, coating adhesion, fabric fire behaviour and hinge cycle life need a laboratory, a separate scope with its own sample and cost.
Decision rule: name the inspection level, the AQL, the defect classes and the laboratory tests in the purchase order. A visual inspection is not a material test.
06Price, payment and delivery terms are audit findings
The commercial documents describe the transaction the audit is testing. A proforma invoice should state seller and buyer, item, specification, quantity, unit price, Incoterm, port, payment terms, lead time, packing and validity. When the specification line holds only a product name, the inspection has nothing to measure.
A 30% deposit with 70% before shipment by T/T puts the payment decision before the shipping documents exist. A letter of credit shifts risk towards documents and adds cost: every discrepancy is a delay.
Incoterms 2020 defines delivery, cost and risk across 11 rules, seven for any mode and four for sea and inland waterway. It does not replace a contract or decide compliance. Naming the rule without the place leaves the transfer point ambiguous.
Decision rule: the invoice carries the Incoterm with its named place, the bank account matches the seller, and the lead time is in working days from deposit and drawing approval.
07Run the audit in one day and score what you saw
Sequence the day so documents are checked before the walk and the walk before the closing meeting. A factory that knows the order of the visit prepares for it, which is itself information.
- Send the document request ahead: licence, certificate, calibration register and recent inspection reports.
- Verify the USCC and the certificate register before travelling.
- Walk the route your product takes, from goods-in to the loading bay, in order.
- Watch the bottleneck for 30 minutes and time three cycles yourself.
- Pull three records at random and trace each to a part and a signature.
- Close with findings that carry an owner, a date and a clause.
Score findings in three bands. Stop means the fix happens before the deposit. Price means the cost of covering it belongs in the quotation. Monitor means a risk you accept and record. Bands beat a score out of ten because they become instructions.
Decision rule: record every finding as what you saw, where, and who owns the fix. A finding without a location, an owner and a date does not survive a change of project manager.
What your RFQ should state
- The seller's legal name, 18-character USCC, registered address and production address, with the bank account name matching the seller.
- The entity that issues the invoice and the entity paid, with the written relationship where they differ.
- The station that limits capacity, the shift pattern assumed and the weekly capacity in your order's unit.
- Every operation that leaves the building, with the subcontractor named and acceptance criteria for each.
- The inspection level, the AQL for major and minor defects, and the sample size drawn from the lot size.
- The laboratory tests required, with method, sample size, laboratory and who pays for a failure.
- The Incoterm with its named place, the port, the payment structure and the lead time in working days.
Where this guidance stops
- This article describes an audit method, not a guarantee of any factory's performance. Findings date quickly: a line idle this month may be fully booked next month.
- A one-day visit samples a site on one day. Order mix and shift patterns change what a line can do, so a second visit during your own production is worth more.
- No photograph or site walk establishes material composition, coating adhesion or fire performance. Those need a laboratory and a stated test method.
- Legal ownership of a production site is a matter for company records and, where it matters commercially, for local advice.
- Foshan Supply coordinates supplier options, samples, production follow-up and inspection against an agreed scope. We do not certify a factory, issue test reports or guarantee a supplier's capacity.
Questions buyers ask
What is a factory audit checklist?
It is a list of what to verify on a supplier site before committing an order: the legal entity, the production address, capacity at the bottleneck, the equipment against your drawing, the records behind quality claims, and the commercial terms on the invoice. Each item should produce a finding, a question or an RFQ clause rather than a tick.
How do I tell a trading company from a factory?
Follow one order through the works. A factory can show the cutting list, the machine that cut the part, the operator's record and the carton label for the same job. A trading company can show samples and prices but cannot trace the part. Both are legitimate; the difference is who carries the production risk.
Does an ISO 9001 certificate prove product quality?
No. It certifies that a management system was audited within a stated scope on a stated date. Check that the scope names your product, that the certification body is accredited and that the certificate is live on the register, then ask for inspection records and a sample report from the last quarter.
What is the difference between a factory audit and pre-shipment inspection?
An audit looks at the system and the site before or during the order: who makes the goods, on what equipment, with what capacity and records. Pre-shipment inspection looks at the goods at the end: quantity, specification, workmanship, dimensions, packing and marks, usually by AQL sampling under ISO 2859-1. Neither replaces laboratory testing.
Which AQL should I use for furniture?
A common starting point is general inspection level II with AQL 2.5 for major defects and 4.0 for minor ones, applied to the lot size to fix the sample. That is a convention, not a rule: a hotel order with visible surfaces may justify a tighter AQL and a critical defect class of zero.
Can a factory audit be done remotely?
Partly. Documents, register entries, calibration records and video walk-throughs can be checked remotely, and they remove the weakest claims before you travel. Capacity, idle lines, work in progress and tooling condition are difficult to judge on a call. Treat remote checks as preparation, not as a substitute.
What should a proforma invoice include?
Seller and buyer, item, specification, quantity, unit price, Incoterm with its named place, port, payment terms, lead time, packing and validity. Add the production address and the bank account name. An invoice that names a product but not a specification gives the inspection nothing to measure against.
Sources
- Incoterms 2020 rules — International Chamber of Commerce
- ISO 2859-1 — Sampling procedures for inspection by attributes — International Organization for Standardization
- National Enterprise Credit Information Publicity System — State Administration for Market Regulation, China
- Importing into the United States — basics for importers — US Customs and Border Protection
- ISO 9001:2015 — Quality management systems: requirements — International Organization for Standardization
- IAF CertSearch — register of accredited management system certificates — International Accreditation Forum
- Harmonized System nomenclature — World Customs Organization
Pages related to this guide
How this guide was checked
- Written from the public catalogue, the standards and regulator pages listed under Sources, and the process records described on the services page.
- Catalogue references and model details were checked on 2026-11-05; 7 primary sources are linked above.
- No supplier paid for placement. No price on this page is an offer; ranges are planning references and must be confirmed in a quotation.