In short

A window schedule is a table with one row for every opening in a building, carrying the size, configuration, frame system, glass build-up, declared performance, finish, hardware and fixing that a supplier has to price. It is issued with the tender, returned with the quotation and attached to the purchase order as the description of what was bought.

Buyers often send drawings instead, and drawings do not price. A factory reading an elevation has to guess the frame depth, the spacer, the weather class and the fixing, and every guess becomes a difference between two quotes that look identical on the last page. The schedule exists to remove the guesses before the prices arrive.

01One row per opening is the whole discipline

A schedule works when the row count equals the mark count on the elevations, because a supplier prices what it can count and nothing else.

The alternative is a note on the drawing set: supply and install as scheduled. That transfers the design decision to the factory, which picks a system it has in stock and a class it can reach without retesting.

Number each opening once. The mark goes on the elevation, on a label fixed to the frame and on the packing list, so the crate opened on site can be matched to the hole in the wall without a telephone call. A large opening made from several units still gets one row per unit.

The rule at issuing stage: if a row cannot be tied to a mark on a drawing, it is not yet an opening. It is an intention, and intentions get priced twice.

02The eleven fields that decide whether quotes compare

Eleven fields carry the decisions, and each one is a place where two quotes can silently diverge while the totals stay similar.

The eleven schedule fields, what each one fixes, and the form in which it should be stated (dimensions in millimetres, U-values in W/(m²·K))
Field What it fixes State as
1. Mark and locationIdentity between drawing, frame label and packingW-01, room, elevation and floor level
2. Structural openingThe hole the frame must fitWidth × height in mm, measured on site
3. Frame overall sizeWhat the factory will actually buildWidth × height in mm, returned by the supplier
4. Configuration and handingSashes, fixed panes, opening direction, sightlineText plus a small elevation sketch
5. Frame system and thermal breakUf and the profile that produces itSystem name, break width in mm, Uf and its method
6. Glass build-upUg and the linear loss at the glass edgePane thicknesses, cavity, gas, coating, spacer, Ug, Ψg
7. Declared UwThe figure a label or declaration claimsUw with the calculation and the reference size
8. Weather classesAir, water and wind performanceEN 12207, EN 12208 and EN 12210 classes plus specimen size
9. Solar and daylightHeat gain and light admittedSHGC and visible transmittance, or the EN 14351-1 declaration values
10. Finish and hardwareColour, coating and moving partsColour reference, coating type, hardware schedule line
11. Fixing and documentsWho installs and what proves the orderFixing drawing, packing mark list, declaration of performance

Adapt the column order to your own tender, then lock it. A schedule that changes shape between issues cannot be compared against an earlier quotation.

Two suppliers can return the same total and different windows. Score each returned quotation against the eleven rows and treat a blank as a question rather than a zero: a quote with ten answered fields is not cheaper, it is unquantified.

Catalogue reference: aluminium windows and exterior doors — models, dimensions and finishes for the directions discussed above.

03The thermal break sets Uf before the brand does

Aluminium conducts heat at roughly 160 W/(m·K) and polyamide 66 with glass fibre conducts at about 0.3 W/(m·K), so the break is the only reason an aluminium window can approach the frame performance of timber.

Its width and chamber count move the frame U-value further than the brand on the handle does.

Indicative frame U-values by thermal break construction, in W/(m²·K). Planning bands, not certified figures for a named profile
Construction Indicative Uf What it implies
Plain aluminium, no break5.6–6.0A shopfront or a cold-climate failure; condensation on the inner face
14.8 mm break3.0–3.5The older standard break; adequate in mild climates, weak in cold ones
24 mm break2.0–2.8The usual residential specification in a heating-dominated market
34 mm multi-chamber1.6–2.2Deep profiles with several chambers; heavier, wider sightline

Bands describe typical constructions. The figure that governs an order is the one the supplier declares for the profile it will extrude, from a test to ISO 10077-2 or from the default values in ISO 10077-1.

A quotation that says thermally broken without a width or a Uf has said nothing comparable: a 14.8 mm break and a 34 mm multi-chamber break occupy different bands, and the span within those bands is roughly a factor of two. Ask which one is supplied, in writing, on the line for each opening.

The clause: state the frame Uf in W/(m²·K), the break width in millimetres and the method behind the number, and require the supplier to confirm the same figures on the order confirmation.

04Uw belongs to a size, so the size goes in the row

Uw is the area-weighted average of frame, glass and the linear bridge at the glass edge: Uw = (Ag·Ug + Af·Uf + lg·Ψg) / (Ag + Af) under EN ISO 10077-1, where Ag and Af are the glass and frame areas and lg is the glass perimeter.

The consequence is that a single Uw describes a single size. Take a 1.20 × 1.40 m opening with a 65 mm frame face: glass area about 1.36 m², frame area 0.32 m², glass perimeter 4.68 m. With Ug 1.2, Uf 2.4 and Ψg 0.05, Uw is 1.57 W/(m²·K). The same build-up on a 600 × 600 mm opening gives 1.92 W/(m²·K), because the frame is a larger share of the area.

Worked Uw calculation for two sizes of the same build-up, after EN ISO 10077-1 (areas in m², perimeter in m, U-values in W/(m²·K))
Quantity 1.20 × 1.40 m 600 × 600 mm
Overall area1.680.36
Glass area Ag1.360.22
Frame area Af0.320.14
Glass perimeter lg4.681.88
Ug / Uf / Ψg1.2 / 2.4 / 0.051.2 / 2.4 / 0.05
Calculated Uw1.571.92

Areas are rounded to two decimals and the Uw values are calculated here, not quoted from a supplier. Substitute the declared Ug, Uf and Ψg for the order.

The instruction that follows is simple and usually ignored: one calculation per distinct size, and a statement of which size the single headline Uw refers to. A supplier returning one number for a building has returned one row of evidence and applied it to the rest.

05The spacer sits in the same line as the glass

A warm-edge spacer reduces Ψg from roughly 0.10–0.12 to 0.04–0.06 W/(m·K), and that linear term is multiplied by the whole glass perimeter rather than by the area.

On the 1.20 × 1.40 m opening above, moving Ψg from 0.11 to 0.05 changes Uw from 1.74 to 1.57 W/(m²·K). That is 0.17 W/(m²·K) on one window, from a component that rarely appears on a quotation and cannot be seen after glazing.

The glass carries the rest: a double-glazed unit typically has Ug 1.0–1.4 W/(m²·K), a triple unit 0.5–0.8, and argon filling improves Ug by roughly 0.1–0.2. Those values cannot be read from a showroom sample, which is a single hand-built unit.

Write the build-up as one unbroken string, for example 6 / 16 argon / 6, low-e, warm-edge, Ug 1.1, Ψg 0.05, and require the order confirmation to repeat it. A substitution that changes the spacer, the gas or the coating is a different window with a different Uw, even when the unit looks identical from a metre away.

06Air, water and wind classes need a specimen size

EN 12207 classifies air permeability 1–4, EN 12208 watertightness 1–9A and EN 12210 wind resistance 1–5, and every class was earned on a specimen of a particular size.

The three European weather classes, their scales, and the extra information a schedule clause must add
Standard Classifies Scale Add to the clause
EN 12207Air permeability1–4Specimen size and test pressure
EN 12208Watertightness1–9ASpecimen size, and whether A or B applies
EN 12210Wind resistance1–5Specimen size and the deflection limit

A class number without the specimen size is a claim about a test piece, not about the opening you are buying. Ask for the report page that states both. Condensation resistance, where a project reports it, is covered by AAMA 1503 in US practice.

The specimen size is the part buyers leave out. A watertightness class earned on a 1.2 m casement does not transfer to a 3 m sliding panel: the span, the sash weight and the drainage path all change, and the larger unit would need its own test.

The US route runs through NFRC 100 and 200, and the NFRC label reports U-factor, SHGC, visible transmittance and air leakage. The label is useful because it names the values and the product line rather than a single adjective, and it still describes the product at the size tested.

CE marking under EN 14351-1 works through a declaration of performance for the product. It declares the unit that leaves the factory, not the wall it is fixed into. A schedule that treats the mark as a site guarantee has confused a product declaration with a completed building.

07How to run three quotes through one sheet

Three quotations become comparable when the returned files carry the same columns, the same row count and the same build-up strings. That is a document problem before it is a price problem.

  1. Issue the schedule as a spreadsheet with a locked column order and one row per mark, not as a PDF.
  2. Ask each supplier to return the same file with four extra columns: unit rate, Uw per size, class, and a deviation note.
  3. Score the blanks first and the prices second; an empty cell is the variation you will meet later.
  4. Require the Uw calculation for the largest and the smallest opening, and check that both use the declared inputs.
  5. Treat any substitution of spacer, glass or break width as a new quotation rather than a discount.
  6. Attach the returned schedule to the purchase order and reference it as the description of the goods.

What your RFQ should state

  1. Price one row per opening mark, with a unit rate for each mark and no allowance for openings that are not listed.
  2. Give the structural opening in millimetres as measured on site, and require the supplier to return the frame overall size it will manufacture.
  3. Name the frame system, the thermal break width in millimetres and the frame Uf in W/(m²·K), with the method behind the figure.
  4. Write the glass build-up as one string: pane thicknesses, cavity, gas, coating, spacer, Ug and Ψg.
  5. State the required air, water and wind classes to EN 12207, EN 12208 and EN 12210, and require the test report to state the specimen size.
  6. Require a Uw calculation for the largest and the smallest opening, not one figure for the whole order.
  7. List the finish, colour reference and hardware line for each opening, and state who supplies the fixings and whether they are thermally isolated.
  8. Require the declaration of performance to EN 14351-1, the packing mark list and the fixing drawing with the quotation.

Where this guidance stops

Questions buyers ask

How many fields should a window schedule have?

Eleven is a working number: mark, structural opening, frame size, configuration, frame system and break, glass build-up, declared Uw, weather classes, solar and daylight values, finish and hardware, and fixing with documents. The test is not the count but whether two suppliers can fill every column without asking a question.

Can one Uw value cover every window in a building?

No. Uw is calculated from the glass area, the frame area and the glass perimeter, so it moves with size: the same build-up gives 1.57 W/(m²·K) at 1.20 × 1.40 m and 1.92 at 600 × 600 mm. Ask for the calculation for the largest and the smallest opening, and ask which size the headline figure refers to.

Is a CE mark enough evidence of window performance?

It is evidence that a declaration of performance exists against EN 14351-1 for that product, and the declaration is where the declared values sit. It is not evidence about the installation or the wall. Ask for the declaration values, the test report with its specimen size and the fixing detail.

How does EN 12207 differ from an NFRC air leakage figure?

Both measure air passing a closed unit under pressure, but EN 12207 sorts the result into classes 1–4 on a European specimen, while the NFRC label reports a leakage rate for a product line tested under NFRC 100 and 200. The two are not convertible. State which route your project requires and ask for the report rather than a class letter on its own.

Should the schedule show the structural opening or the frame size?

Both. The structural opening is measured on site and belongs to the builder; the frame overall size is what the factory will make. State both in the row and require the supplier to confirm the frame size before fabrication starts.

Does a wider thermal break always mean a lower Uw?

Not automatically. A wider break usually lowers Uf, which lowers Uw, but Uw also depends on the glass area, Ug, Ψg and the ratio of frame to glass. A fixing or hinge that crosses the break short-circuits it locally, which is why fixing position and hardware isolation matter as much as the break width on the drawing.

Who should supply the window fixings?

Decide before the order rather than on site. If the window supplier provides them, the fixing detail and the thermal isolation travel with the frame and responsibility is single. If the main contractor provides them, the schedule must still state the fixing specification, the position relative to the break, and who confirms the reveal dimensions. Either way it is a schedule line.

Sources

  1. ISO 10077-1:2017 — Thermal performance of windows, doors and shutters: calculation of thermal transmittance — International Organization for Standardization
  2. ISO 10077-2:2017 — Thermal performance of windows, doors and shutters: numerical method for frames — American National Standards Institute webstore
  3. EN 14351-1 — Windows and doors: product standard, harmonised specification — European Committee for Standardization
  4. NFRC ratings, certification and product labelling — National Fenestration Rating Council
  5. NFRC energy performance label: the values reported — National Fenestration Rating Council
  6. AAMA 1503 — Voluntary test method for thermal transmittance of fenestration systems — American Architectural Manufacturers Association
  7. CE marking: the rules for construction products — European Commission

Pages related to this guide

How this guide was checked

FS

Foshan Supply editorial team · Catalogue indexMethodology

Written in Foshan and reviewed against the catalogue and public standards on 2026-11-05. This page is a buying guide, not a quotation or a warranty. How we work.