In short

An FF&E budget is the total cost of furniture, fixtures and equipment from the purchase order to the standing room, a wider figure than the sum of the supplier prices on the schedule. The furniture is one layer. Freight, duty, inland delivery, installation and the contingency that absorbs the mistakes are five more, each bought from a different company.

This matters because the quotation answers a narrower question than the budget. A supplier can price a schedule accurately and still leave the buyer short of the money needed to open the doors, because the quotation stops at the port. The gap is rarely one large error. It is six small ones, and the contingency pays for all of them.

01Six cost layers sit between the schedule and the installed room

The supplier price covers one of the six layers that decide what a furnished room costs, and it is the only one most buyers can see. The other five are bought separately, each with its own unit, document and person who can move the number.

The six layers of a hotel FF&E budget, the unit each is charged on, and the record that proves the figure.
Layer Charged on Evidence to keep Bought by
Furniture pricePer item, per finish, at the agreed IncotermPurchase order with approved drawing referenceOwner, through the supplier
Freight and insurancePacked cubic metres and gross kilograms, by modeBooking note, packing list, insurance certificateForwarder
Duty and clearanceTariff code, origin and customs valueCommercial invoice, customs entry, broker sheetImporter of record
Inland delivery and hoistingKilometres, access, lift or crane timeDelivery note, site access planLocal transport contractor
InstallationRoom type and labour hoursMethod statement, signed room sheetInstall crew
Contingency and attic stockA stated percentage of the five layers aboveVariation log, spare stock list, storage addressProject owner

Attic stock is the replacement reserve held for damage in service; it is bought at contract price and stored somewhere, so budget both.

Put each layer on its own budget line with a named owner. A single delivered figure cannot be compared with a layered one, because the first hides which of the five decisions has already been taken. Work to a stated contingency — 10% of the five cost layers is the figure this article uses — and name the one person allowed to release it. Decision rule: six cost lines, six owners and one release authority.

02Freight is charged on carton volume and weight, not on the invoice

Groupage is charged on W/M, where one revenue ton is 1 m³ or 1,000 kg, whichever is greater. Take a sofa of 60 kg packed into 1.4 m³ of carton: it pays for 1.4 revenue tons, so the packing is being bought. Upholstery fills a container on volume before it reaches the weight limit.

Chargeable basis by freight mode, and the number that decides the invoice.
Mode Chargeable unit What decides the figure Clause to add to the RFQ
LCL groupageW/M: 1 m³ or 1,000 kg, whichever is greaterMeasured carton volume after packingPacked dimensions per item in millimetres; no estimates from product size
FCL, 40 ft high-cubeCubic metres used and payloadCarton stack height and floor loadingCarton count, stackability, and whether cartons may be double-stacked
AirChargeable weight, about 167 kg per 1 m³Volumetric weight against actual weightGross weight per carton and total shipment weight
Consolidated groupageW/M, plus a handling charge per shipmentNumber of suppliers feeding one containerPickup address and ready date per supplier, with a cut-off

A 40 ft high-cube is a planning reference of about 76 m³ and roughly 26,500 kg payload; a 20 ft is about 33 m³. The booking note states the figures that apply to your container.

The common failure is a budget built from product dimensions. A sofa 2,200 mm long is not 2,200 mm of carton: wrapped arms, corner protection and a pallet add volume on every side, and the forwarder re-measures at origin after the budget is signed. The difference comes out of the contingency. Prevent it with one clause: state packed length, width and height in millimetres and gross weight in kilograms for every item, with the carton count, and make the freight price conditional on those numbers. Decision rule: no freight figure without packed dimensions and a gross weight for every item.

Catalogue reference: hotel and resort furniture projects — models, dimensions and finishes for the directions discussed above.

03Duty follows the tariff code, and the code follows the material

Customs classifies goods by what they are made of, not by what the room is called. An upholstered sofa on a hardwood frame, a metal-frame side chair and a veneered desk can land in three tariff lines with three rates, turning on the frame, the filling and the fabric composition. The fabric specification therefore has a customs consequence as well as a durability one.

The Incoterm decides who is the importer of record and therefore who pays. DAP leaves duty and clearance with the buyer. DDP puts them on the seller, which is convenient and opaque: the rate sits inside the price where nobody can audit it. Price at the Incoterm you can insure and clear yourself, and ask for the code before the order.

Ask for the rate as a percentage and the value it applies to, because destinations differ on whether freight and insurance form part of the customs value. Two decimal places and a named valuation basis make the line auditable. Decision rule: a duty line without a code, a rate and a valuation basis is a guess with a decimal point.

04Installation is a separate purchase with its own scope and hours

Installation is not delivery. It is unpacking, assembling, fixing to the wall where anti-tip is required, positioning to the drawing, protecting the floor, removing packaging and signing the room. Each of those is labour, and labour is priced per hour or per room, not per cent of the furniture value.

Layout is where the installation budget meets compliance. The 2010 ADA Standards require clear floor space of 760 × 1,220 mm at the bed, the seating and the controls in an accessible guestroom, plus a 1,525 mm turning circle. A drawing can show those zones and still ship a room that fails, because the crew placed the desk where it was easier to carry. The install drawing must carry the clear zones.

  1. Count rooms by type and list the items and quantities in each type.
  2. State the access: lift dimensions, stair width and the distance from the loading bay to the furthest room.
  3. State the hours allowed per room type for assembly and fixing, and who signs the room sheet.
  4. State who supplies floor and lift protection, and who removes the packaging from site.
  5. State the snag window and who pays for a return visit after the room is signed.

Then price it per room type. A single percentage of the furniture value hides a suite with fourteen items behind a room with six. Decision rule: the installation line is hours multiplied by the rate you were given, priced per room type, with the access conditions beside it.

05The mock-up room is the last cheap decision

The mock-up room exists to settle the drawing, the finish, the seam position and the hardware before the line starts. Treat it as an approval record rather than a showroom: its cost is one room set against the whole order. The expensive decision is taken later, once the material is cut.

What a change costs, by the stage at which it is made, and the record that keeps it visible.
Stage What the change touches Who normally pays Record to keep
Before the order cut-offDrawing revision only; no material committedSupplier, inside the quoted priceRevised drawing with a revision letter
After cut-off, before productionMaterial re-plan and a lost place in the queueBuyer, as a variationVariation order with price and date
During productionPart-made components and rework timeBuyerRework note or concession, signed
After shipment, on siteReplacement unit, second freight, second install visitBuyer, unless the fault is the supplier'sSnag list, photographs, claim reference

One mock-up room against a multi-room order is a small share of the furniture value; a change during production can touch every unit in the run.

Sign the mock-up as a specification and list the item numbers, the fabric reference, the finish code and the hardware on the approval sheet. From that signature the schedule is frozen. Anything after it is a variation order, priced and dated before work restarts. Decision rule: the signature freezes the specification, and only a dated variation order moves it.

06Where the 10% actually goes

The contingency is not lost in one event. It drains through six small ones, and each has a clause that closes it.

Decision rule: release contingency only against a variation number, and log every draw with the layer it came from. At the end of the project that log is the honest answer to why the budget moved.

07Build the budget sheet so a supplier can price it

A budget sheet is a schedule with four cost columns added. If the schedule is sound, the budget is arithmetic; if it is a mood board, no amount of costing makes it firm.

  1. Start from the FF&E schedule and do not retype it: item number, room type, quantity, dimensions, finish, fabric, drawing reference and installation date.
  2. Add packed volume in cubic metres, gross weight in kilograms, tariff code and installation hours as four new columns.
  3. Price two Incoterms for the same goods, usually FOB and DAP, so freight and duty are visible instead of buried.
  4. Sum by room type and by cost layer, and keep the two totals side by side.
  5. List every assumption with the name of the person who confirms it, and the date they confirmed it.

When two quotes differ and the scope columns match, the difference is margin or a missing layer. Ask which layer is missing before negotiating the price, because the cheaper quote is often the one that left installation out. Decision rule: compare the layers before the totals, because the missing layer is the first question, not the last.

What your RFQ should state

  1. Packed length, width and height in millimetres and gross weight in kilograms for every item, with the carton count.
  2. The Incoterm the price is fixed at, and the Incoterm the budget assumes for freight, duty and delivery.
  3. The tariff code and country of origin per line, with the duty rate confirmed in writing by the broker.
  4. Installation priced per room type with hours and access conditions, and who signs each room.
  5. The mock-up room as a priced line, with the approval sheet listing item numbers, fabric references, finish codes and hardware.
  6. A stated contingency percentage and the one person authorised to release it, with a variation number for every draw.
  7. Attic stock as a percentage of each loose-furniture item, with the storage address and the person responsible.
  8. The claim window for transit damage, who pays freight on a replacement, and the photographs required with a claim.

Where this guidance stops

Questions buyers ask

What percentage of an FF&E budget should be contingency?

There is no standard figure, but 10% of the five cost layers is a common planning allowance for a project with a frozen schedule and an approved mock-up. Below that, one re-measured container or one change after the order cut-off will exhaust it. State the percentage, name the person who releases it, and log each draw against a variation number.

Is an FF&E budget the same as the furniture quotation?

No. The quotation prices furniture at an agreed Incoterm and usually stops at the port or the supplier's yard. The budget adds freight, insurance, duty, inland delivery, hoisting, installation, attic stock and contingency. Two quotes can be identical and still produce budgets that differ by the cost of getting the goods into the rooms.

How is hotel furniture freight calculated?

Groupage is charged on W/M, where one revenue ton is 1 m³ or 1,000 kg, whichever is greater. Full-container freight is charged on the container and limited by the cubic metres the cartons use. Air freight is charged on chargeable weight, about 167 kg per 1 m³. In every mode the packed carton is the unit being bought.

Who pays import duty under DAP and DDP?

Under DAP the buyer is the importer of record and pays duty, tax and clearance. Under DDP the seller arranges and pays them, and the cost sits inside the price. DDP is convenient but hard to audit, because the rate and the code are not shown. Ask for both either way, and check which Incoterm the quotation and the budget each assume.

Should installation sit in the FF&E budget or the construction contract?

Put it in the FF&E budget as its own line. Installation of loose furniture usually sits outside a joinery or fit-out contract, and a percentage allowance hides the rooms with the most items. Price it per room type with hours, access conditions, protection and a snag window, and name who signs each room at handover.

Why does the tariff code change the budget?

The code sets the duty rate, and it follows the material and construction: frame species, filling, fabric composition and whether the piece is seating or storage. Two items that look alike in a photograph can sit in different lines. If the code is confirmed late, the rate changes after the budget is signed and the difference lands on the contingency.

How should replacement stock be budgeted?

Buy attic stock as a stated percentage of each loose-furniture item, commonly 2% to 5% as a planning range, and budget the storage as well as the goods. Record the item number, finish and fabric batch so a replacement matches. Stock held without an address and an owner is a second purchase later, at a higher price.

Sources

  1. ANSI/BIFMA standards for office and contract furniture — BIFMA International
  2. Technical Bulletin 117-2013 — smoulder resistance of upholstered furniture — California Bureau of Household Goods and Services
  3. BS EN ISO 12947-2:2016 — abrasion resistance of fabrics by the Martindale method — BSI
  4. ASTM D4157 — abrasion resistance of textile fabrics, oscillatory cylinder method — ASTM International
  5. 2010 ADA Standards for Accessible Design — US Department of Justice
  6. Incoterms 2020 rules — International Chamber of Commerce
  7. Harmonized Tariff Schedule of the United States — US International Trade Commission
  8. Harmonized System nomenclature — World Customs Organization

Pages related to this guide

How this guide was checked

FS

Foshan Supply editorial team · Catalogue indexMethodology

Written in Foshan and reviewed against the catalogue and public standards on 2026-11-05. This page is a buying guide, not a quotation or a warranty. How we work.

How to cite this page: Foshan Supply, “FF&E budget: the 10% contingency that disappears”, 2026-11-05, https://foshansupply.com/blog/ffe-budget/